They stated Maintained Bord and pillar development mining systems
-121 Panel “super unit”
- 103 Panel “single unit”
- 200 Panel “pillar quartering”
![]() |
Click to enlarge |
Maintain(powerpoint)
Production levels continue to achieve budget and forecast
Employee numbers increased by 1 persons to 64
Process improvements initiatives continue to deliver increased productivity and lower cost.
Focus on monitoring and improving coal quality and awareness of marketing options
Currently supplying both domestic (Eraring) and export customers through Port Kembla and Newcastle
Feasibility study on Phase 2 Mining Development continued
From information supplied to CVA Inc.
No comments:
Post a Comment